Barnstead NH Cell Tower: Why Verizon Wants to Move Down Province Road

November 12, 2026

At 708 Province Road, a driveway off Parade Hill Road leads to a corn field. Tonight at 6 p.m. at Barnstead Town Hall, the Planning Board continues its review of a plan to put a 195-foot self-supporting communications tower on a leased piece of that parcel. Barnstead already has a 190-foot self-supporting tower at 26 Hartshorn Road, about 0.52 miles away. The applicant told the board it knows of no other towers within town limits.

So a small town would end up with two tall towers about half a mile apart. According to the applicant's own testimony in the town record, the main reason is the rent on the first one.

The Reason on the Record Is the Rent

Harmoni Towers Gateway, LLC, of Charlotte, North Carolina, filed the application. Harmoni says Verizon Wireless hired it to build the tower. At the board's September 3, 2026 meeting, the applicants explained why Verizon wants a new structure instead of staying on the existing one. The approved September 3 minutes record it this way:

"It is economically prohibitive for them to be at that site because the rent, which is astronomical, is way above market rent."

Will Dodge, the Downs Rachlin Martin attorney representing Harmoni, told the board that Verizon had "run the numbers" and that "all their attempts at negotiations have failed." He also said Verizon believes the Hartshorn Road tower is at or near the end of its useful life. The applicants told the board that towers usually last 30 to 40 years, which is also a common lease term, and that many towers built in the 1990s and early 2000s weren't designed for ice and wind loads the way current standards require.

The existing tower would stay up. Verizon would take its antennas and ground equipment off the Hartshorn Road structure and put them on the new one, and other carriers could stay where they are. Board members asked whether residents would lose coverage if the new tower were never built. The applicants said they "could not say with certainty," and added that coverage concerns can involve capacity as well as geographic gaps.

By the October 15 meeting, Verizon's side still wasn't giving any figures. The October 15 minutes record Attorney Dodge saying the clients would not disclose the rents "because a lot of that is trade secret." He also said that if the tower is approved and built, Verizon has committed to be at least one co-locator.

A National Lease Fight Reaches Parade Hill Road

From Town Hall, this can look like a local disagreement. It matches a pattern the wireless industry has been describing for over a year. In October 2025, Inside Towers reported that, according to RBC Capital telecom analyst Jonathan Atkin, Verizon had "recently embarked on a high-rent relocation program." Atkin named American Tower as the main target because it is Verizon's largest tower landlord and its master lease with Verizon was due to expire within two years.

The same piece describes how the economics work. Master leases let a carrier make changes on a tower without extra charges, but they "tend to be more expensive than an à la carte approach" and usually include fixed annual escalators. Tower owners like them because the income is predictable. Inside Towers also reported that Verizon paid American Tower $341 million in the second quarter of 2025, about 27 percent of American Tower's domestic leasing revenue. Carriers are still adding sites for capacity while looking for ways to hold down operating costs, and "achieving lower tower rents is one avenue."

The October 15 minutes identify the Hartshorn Road structure as the existing ATC tower. A carrier facing years of rising rent can pay for a new tower nearby, and that choice is now coming up on a Barnstead road.

Questions Before the Board

The board has argued over the application at both meetings. One board member said he saw "no public need" for a tower that adds no coverage or service. Another member worried that approving a tower justified only by rent could set the board up for a later denial "based on lack of evidence." Attorney Dodge answered that the site plan regulations contain no "need case" requirement. He said the same goes for the state telecommunications statute that the town's regulations incorporate in Appendix D.

On October 15 the board voted 3 to 2 to ask town counsel whether it must accept the application as complete when there is no perceived community benefit and the applicant has presented no evidence of a capacity gap.

What Would Stand on 0.13 Acres

Item As presented to the Planning Board
Height 195 feet, plus a 4-foot lightning rod
Leased compound 100 by 100 feet, with access from the road
Land Use Tax area Corrected to 0.13 acres from an earlier 13
Access Shared driveway on Parade Hill Road
Lighting FAA found no hazard; marking and lighting not required
Room to grow Designed for two additional co-locators
Upkeep Unmanned, monthly visit by one person in a small truck

The generator got the closest questions. Board members asked how a propane generator compares with a diesel one for noise. Craig Russo of T-Squared Site Services, who joined the applicant's team by Zoom, calculated that three of the same generators running together would reach 85 decibels, since sound adds on a logarithmic scale. A board member suggested an exhaust silencer, and Attorney Dodge said he would look at further sound reduction. The applicant also still has to add the State to the tower removal bond. The utility "power walk" can't happen until the driveway permit is issued, because that permit generates the E911 address the power company needs before it will come out.

A Lease Lasts as Long as the Tenant's Numbers Work

A tower lease can bring a landowner income for decades, and a tower can shape a neighborhood's views and signal for just as long. The Barnstead record shows both depend on a carrier's cost math as much as on geography. If Verizon decides a structure costs too much, it can pay to build a new one half a mile away. That moves the visual impact to "a different set of neighbors," in the board's words from September.

It also shows that a tower going up doesn't have to mean coverage is improving. The applicants said the Province Road site is meant to "replicate or at least not lose existing coverage" and to connect with other sites. They gave the main reason as keeping Verizon's equipment in service on affordable terms. Harmoni builds the same kind of tower in other places. The Town Line reported that China, Maine's Planning Board unanimously approved a 195-foot Harmoni tower on Parmenter Hill after a September 22 public hearing at which nobody testified.

For a buyer looking at land near Province Road, Parade Hill Road or Hartshorn Road, the planning record is public. These minutes describe height, lighting, generator noise and driveway location in more detail than any listing would.

Tonight's Agenda at Town Hall

The November 19 meeting starts at 6 p.m. The agenda includes:

  1. A continued minor subdivision review for 919 North Barnstead Road, splitting one parcel into three lots, with a public hearing to follow.
  2. The continued Harmoni Towers site plan review for 708 Province Road, with a public hearing to follow.
  3. A public hearing on the 2027 Capital Improvements Program.
  4. A public hearing on naming the Road Agent as the board's designated agent for driveway permits.
  5. A work session on reviewing and updating the zoning ordinance.

At the September meeting, the chairman told abutters there would be no public hearing until the application was complete. Written comments had already been submitted.

Quick Questions

Would the existing Hartshorn Road tower come down? No. The applicants said Verizon would move its antennas and ground equipment to the new tower, and other carriers could stay on the existing one.

Would the new tower be lit at night? The FAA determination in the application found the tower would not be a hazard to air navigation and that federal law does not require marking or lighting.

Where can residents read the full application? The October minutes say the surveys and supporting materials are in the applicant's binder at the Planning Board clerk's office.